How long would a buyer wait for one of the 150 condominiums Pulte has proposed for the Meadow Plaza site on Cherry Lane? Pulte's own schedule assumes the Village approves the plan by the end of 2026. Even then, first closings would come in late fall 2028, and the second and third buildings would start in summer 2028 and spring 2029, depending on sales.
The price matters as much as the wait. Pulte's target for these units is $600,000 to $1 million each. In October 2026, the median sold price for all of Northbrook was $706,000. That figure combines single-family homes with condos and townhomes, according to the RPR market report linked from the North Shore-Barrington Association of REALTORS. Northbrook's new condos and townhomes are being priced in the same range as the town's typical home sale. A buyer looking at the Flats at North Branch is effectively comparing it with a house, and with a calendar that runs two years ahead.
The calendar comes before the price
The Meadow Plaza proposal is still working through the Village's public process. Here is the sequence a buyer would be waiting on, in the order Pulte and the Village have laid it out:
- Plan Commission hearing. It opened October 6 and continued October 20 and 21 without a decision. The Village set the November 17 session at Techny Prairie Activity Center, limited to testimony about Pulte's revised plans.
- Village Board decision. The Plan Commission only makes a recommendation. The Board of Trustees has final authority.
- Building permit review. Even after a zoning approval, the developer still has to pass a detailed permit review.
- Demolition and site work, starting spring 2027 if approval comes by the end of 2026.
- First building, at Meadow and Cherry, starting fall 2027, with first closings in late fall 2028.
- The other two buildings, starting summer 2028 and spring 2029, depending on sales.
The last step is the one that affects a buyer's timing most. The second and third buildings start as units sell, so the date a buyer gets keys depends on which building the unit is in.
The plan has already changed during the hearing. Commissioners asked why roughly 90,000 square feet of existing retail would shrink to about 11,000 square feet in the original proposal, and they raised floodplain limits on underground parking, as Citizen Portal's coverage of the October 6 session reported. Pulte's revised narrative dated November 6 enlarges one commercial building from 5,500 to 7,000 square feet. It drops the riverwalk and pond and adds a 0.79-acre Village Square with 11 small incubator shops, which Pulte would build and give to the Village.
Where the target price lands
| Home | Size | Price point | Time frame |
|---|---|---|---|
| Northbrook condo resales, median sale | Varies | $380,000 | October 2026 sales |
| Highest-priced Northbrook condo listed | Varies | $699,900 | As of November 11, 2026 |
| All Northbrook sales, combined median | Varies | $706,000 | October 2026 sales |
| The Flats at North Branch, proposed | 1,177 to 1,703 sq ft | $600,000 to $1 million target | November 6, 2026 plans |
| Reserve at the Brook townhomes | 2,625 to 2,763 sq ft | Starting in the mid-$800,000s | Current builder pricing |
According to Midwest Real Estate Data figures for October 2026, Northbrook's resale condos sold at a median of $380,000. As of November 11, the most expensive condo on the market was listed at $699,900. The bottom of Pulte's target range is already near the top of today's resale condo market. The upper end reaches well past it, into the price range where Northbrook's single-family homes compete. That makes resale condos a weak benchmark for these units. The real alternatives are a house, or one of the new townhomes going up across town.
The Reserve at the Brook makes the same point from another direction. Pulte's Reserve at the Brook townhomes start in the mid-$800,000s for 2,625 to 2,763 square feet, with a first-floor owner's suite, in a community for buyers 55 and older. At the upper end of the Flats range, a buyer would pay more for roughly 1,700 square feet on one level than the Reserve's starting price for more than 2,600 square feet. The two products serve different needs, and the difference shows how much of a new condo's price goes to location and building.
How a shopping center becomes a six-story condo building
The proposed prices follow from what the site needs to become housing. Meadow Plaza covers about seven acres, 6.94 in the November plans, and its roughly 90,000-square-foot shopping center would be demolished entirely. The Village has said it "cannot require a private property owner to redevelop or prohibit them from submitting a proposal." Over the past seven years, the owner renegotiated tenant leases with 90-day termination provisions to leave room for future redevelopment.
Zoning sets the height. According to The Northbrook Report's summary of Pulte's filed application, the site is zoned C-2 Neighborhood Commercial within the Village Green Overlay District. That allows four stories and 55 feet by right, five stories and 65 feet with a special permit, and more height inside a planned development. A project that fully complies with the Inclusionary Housing Ordinance may qualify for one more story or up to 12 more feet, subject to Board approval. Pulte has asked for six stories and 68 feet. Its plan includes 23 permanently affordable ownership units among the 150.
The building design adds cost of its own. The ground floor of each building is indoor parking, with the residential floors stepped back above it. Of 168 resident parking spaces, 117 are in the building garages. The exterior is brick with Hardie Board siding and trim. Structured parking, a public square handed over to the Village, and the affordable units all have to be paid for out of the project's sales. Most of that falls on the 127 market-rate condos. A target range that starts at $600,000 reflects that math as much as the Northbrook address.
The rest of the pipeline points the same way
Meadow Plaza is the largest proposal, but the Village's development tracker, last updated November 9, 2026, shows a broader pattern in Northbrook's new for-sale housing:
- Reserve at the Brook, 3700 Dundee Road. 53 age-restricted townhomes, eight of them designated affordable. Pulte took over the approved project in January 2026. The church on the site has been demolished, the first several townhomes are under construction, and a model is open.
- Lexington's townhomes, 1825 Shermer Road. The Board approved the final plan for a 53-unit residential planned development on July 28, 2026. The Village posted the approval in a July announcement.
- Northgate Estates, 2420–2450 Landwehr Road. A seven-lot single-family subdivision by Amazing Homes Developer. Site work is finished, and some homes are under construction while other permits are in review.
Counting Meadow Plaza, that comes to 256 attached for-sale homes across three projects and seven new single-family lots. Northbrook's new construction is mostly condos and townhomes, built where churches and shopping centers stood, at prices close to what existing houses sell for. The same pattern has shaped plans at Northbrook Court, where the Village amended the master plan in March 2025 to let residential construction come before or alongside the retail.
The resale market a buyer lives in meanwhile
For anyone considering a condo that would close in 2028 or later, today's market still matters, especially for a household that would be selling its current Northbrook home. In October 2026, Northbrook had 2.23 months of inventory across all property types, up 25.3% from a year earlier. Homes sold at 100.3% of list price, with a median of 12 days on market. Supply is up from last fall, but well-priced homes still sell quickly and at full price. A seller who plans around the Flats is planning around a pre-construction purchase in a building that has not broken ground, while the house they would sell is in a market that moves within weeks.
Reserve at the Brook is further along. Its first townhomes are under construction and a model is open, though Pulte's page gives no completion date. For a buyer who wants new construction in Northbrook, the choice depends partly on which project fits their own sale timeline.
Questions buyers are asking about Meadow Plaza
Is the Flats at North Branch approved? The Plan Commission makes a recommendation, and the Village Board of Trustees makes the final decision. The Village's Meadow Plaza project page posts the filed documents as the case moves forward.
Where exactly is it? At 1901–1975 Cherry Lane, the current Meadow Plaza shopping center site, with buildings along Cherry Lane, Meadow Road and the river. Pulte's first building would go up at Meadow and Cherry.
What are the units like? One-bedroom-plus-den and two-bedroom layouts of about 1,177 to 1,703 square feet, in three six-story buildings of 50 units each.
Who is tracking the hearing in detail? The Northbrook Report maintains a standing page that links each filing, notice and meeting recording.
If you're weighing a Northbrook house against new attached construction, or deciding when to sell so it fits a 2028 closing, Lotzof Malk Residential can map out both timelines with you, starting with a current valuation of your home. Start the Conversation.